Overview of the offshore renewable energy regime

The offshore renewable energy regime is governed by the Offshore Renewable Energy Act 2026 and related regulations, which provide the legislative framework for the investigation and development of offshore renewable energy projects in New Zealand.

The purpose of the regime is to:

  • give developers greater certainty to invest in offshore renewable energy developments
  • allow the selection of offshore renewable energy developments that best meet New Zealand’s national interests
  • manage the risks to the Crown and the public from offshore renewable energy developments.
offshore renewable energy regime on a page

Stages of the regime

The regime consists of a 2-stage permitting system: feasibility permits and commercial permits, and is made up of 4 key stages:

  1. Feasibility – developers apply for a feasibility permit (7-year duration) and carry out activities to determine if their proposed project is viable.
  2. Construction – if the project is viable, feasibility permit holders can apply for a commercial permit (valid up to 40-year duration) to begin building and operating offshore renewable energy infrastructure, subject to relevant environmental consents and any other approvals.
  3. Operations and Maintenance – developers must continue to meet legal requirements, follow permit conditions, and complete annual reporting activities while the project is operating.
  4. Decommissioning – at the end of its life, developers and owners of transmission infrastructure are responsible for removing their infrastructure.

Stages of the regime: offshore renewable energy project

Stages of the regime offshore renewable energy project

Feasibility permits

A feasibility permit provides developers an exclusive pathway to apply for a commercial permit for the same area in the future. This pathway provides developers with greater certainty over future development rights in the area for the construction of their offshore renewable energy project. This means developers are more likely to pursue offshore renewable energy projects, including carrying out feasibility studies on the area.

Applying for a feasibility permit

The Minister is responsible for launching application rounds, during which developers can apply for a feasibility permit.

In launching a round, the Minister will provide key details such as:

  • opening and closing dates for applications
  • eligible permit area locations
  • any limitations to which applications are subject (for example, the type of technology and generation capacity).

The Minister for Energy is responsible for deciding whether to grant a feasibility permit to a developer.

Feasibility permit duration

Feasibility permits will be granted for 7 years. In exceptional circumstances, feasibility permits may be extended for up to an additional 7 years if specific criteria are met, in accordance with the Offshore Renewable Energy Act 2026.

Application fee and annual levy

Applicants for a feasibility permit must pay an application fee when submitting an application. This fee helps recover the costs of assessing applications.

If a feasibility permit is granted, permit holders must also pay an annual levy. This levy is divided among all feasibility permit holders and supports the ongoing administration, monitoring, and regulation of the offshore renewable energy regime.

What happens during the feasibility period

During the feasibility period, developers undertake activities to assess whether their project is technically, commercially, environmentally, culturally and socially feasible.

These activities may include:

  • geotechnical and geophysical surveys
  • wind speed measurements
  • environmental and ecological impact assessments
  • engineering and design studies
  • economic analysis
  • onshore and human impact studies, such as visual impact
  • assessing grid connection options.

Development of the offshore renewable energy regime

The design of the regulatory regime is summarised in the Departmental Disclosure Statement for the Offshore Renewable Energy Bill.

Public consultation on developing the regime

We held 2 rounds of public consultation in December 2022 and August 2023 to inform the development of the regime. Feedback generally supported the proposed settings.

We also carried out targeted consultation on the regulations that form part of the regime.

Read the consultation papers below

Enabling Investment in offshore renewable energy

We consulted on proposed approaches to enabling feasibility studies for offshore renewable energy developments. We received 59 submissions from a wide range of stakeholders and iwi.

Developing a regulatory framework for offshore renewable energy

We sought feedback on proposed regulations to enable offshore renewable energy developments. This was the second discussion document for public consultation on proposals for offshore renewable energy regulation and we received over 50 submissions.

Cost recovery for the offshore renewable energy regulatory regime

Developers with a declared interest in New Zealand and with relevant iwi and hapū were invited to provide views on the proposed fees and levies to fund the regulator functions for the offshore renewable energy regime.

Cabinet decisions on the design of the regime