Get familiar with the legislation and regulations
Familiarise yourself with the Offshore Renewable Energy Act 2026 (the Act) and the Offshore Renewable Energy Regulations 2026 and the Offshore Renewable Energy (Levies) Regulations 2026 (the Regulations).
Offshore Renewable Energy Regulatory Framework and Regime
Read the relevant application round notice
A feasibility permit application may only be submitted during the application submission period set out in the current application round notice.
Your application must comply with any requirements and/or limitations set out in the round notice, along with the requirements of the Act and Regulations.
If you are granted a feasibility permit you must comply with the conditions set out in the round notice. Note that permit-specific conditions may also be applied to individual permits when a permit offer is made.
Offshore Renewable Energy Feasibility Permit Application Round Notice 2026
Pre-application consultation with Māori
Before applying for a feasibility permit, applicants must engage with relevant Māori groups, including iwi, hapū and Treaty settlement entities who have rights and interests in the area where the development is proposed.
Consultation should be broad and inclusive and should identify and assess the potential or expected impacts of the proposed development on these rights and interests.
Applicants should begin planning and preparing for consultation early to allow sufficient time for meaningful engagement and for the outcomes of consultation to inform the proposed development. Clear records of all engagement activities, including meetings, correspondence, and feedback received, should be documented, as information about engagement must be provided as part of a feasibility permit application.
Further guidelines when considering and planning consultation:
Crown engagement with Māori(external link) — tpk.govt.nz
Application guidance
This guidance is intended to help applicants prepare a feasibility permit application. It sets out the supporting documents that should be provided, the information those documents should contain, and MBIE's intended approach to the application and assessment process.
It does not replace, alter, or override any requirements under the Act, Regulations, or other applicable New Zealand law, and has no binding legal effect. Applicants are responsible for ensuring that their application complies with all legislative requirements.
Applicants should read this guidance alongside the relevant legislation and application round notice, which are the authoritative sources of the requirements for applying for a feasibility permit, including any requirements or limitations that apply to a specific application round.